The Lake Planning Commission updated their bylaws with a Resolution on Thursday, June 26, changing their site plan submission deadline.
They also approved two site plans and discussed issues regarding a property on Leach Rd., in which the owners seek to replace an aged manufactured home with a tiny house.

Bylaw Change
In May, Kevin and Tracy McArther submitted their initial survey and site plan the morning of the Planning Commissionβs meeting.
Since they did not meet the 10-day deadline, they had to wait until Juneβs meeting for approval.
This delayed their new homeβs construction timeline by a month.
During that meeting, commission members discussed possible ways to amend the process, in hopes to prevent delays caused by the deadline.
Community planner Donny Bunton returned in June with a proposal.
As Bunton explained, the new resolution βlessens the submission deadline for residential lakefront site plans,β while still allowing enough time to meet a new state requirement that agendas be posted online at least 48 hours before a meeting.
βReally all you’re looking at is, does this proposed house meet the lake setback?β Bunton said. βThat’s really the only thing we look at.β
The revised language states that all items must still be submitted 10 days in advance, except residential lakefront site plans, which may now be submitted as late as the end of the business day the Friday before the meeting.
However, βin the event that additional time is needed to reviewβ any such site plan, βthe Planning Commission reserves the right to defer action until the next regularly scheduled meeting.β
Commissioners voted to approve the resolution, which took effect immediately.
Leach Rd. Property Issue
Commissioners also discussed an issue involving a property at 315 Leach Road, where Lori Moore, along with property owner Richard Chaney, hopes to remove one of two existing mobile homes and replace it with a tiny house.
According to Bunton, the current setup exceeds zoning limitations, but was grandfathered in when the Planning Commission began enforcing zoning regulations in the area.
βRight now, they have two structures on one lot,β he said. βAccording to your zoning resolution, you can only have one principal structure per lot.β
Vice Chair Cayce Maddox, who presided over the meeting in the absence of Chairman John Austin, asked Bunton, βSince itβs grandfathered in, do the rules allow them to replace one mobile home with another? Could they put a newer home on there, or can they just not have an additional structure?β
Bunton replied that you cannot replace a nonconforming with another nonconforming.
While the two existing homes are grandfathered in, replacing one with a new structure triggers the need to subdivide the property.
But therein lies the problem.
βThey donβt have enough road frontage,β Bunton explained.

The property only fronts Leach Road by approximately 18 feet. In order to meet subdivision regulations, the new lot would require a 50-foot access easement, and the existing 18-foot strip is already used by a landlocked cemetery behind the property.
βIf your access easement is serving two lotsβwhich this would beβthen it has to meet county road standards,β Bunton said.
That includes engineering plans, a 50-foot right-of-way, and building the drive to road specifications.
βYou donβt have to dedicate it as a public road,β he said, βbut you have to build it like it is one.β
Bunton noted the unique nature of the situation, especially with the cemeteryβs involvement.
βEvery other property doesnβt have a cemetery behind it,β he said. βThis one does.β
He mentioned the possibility of a creative solution.
βIf [the commission] said, βwe can allow this one lot, because of the cemetery thing, thatβs kind of something unique to this property,ββ Bunton said. βThat would be a compromise.β
Still, he said that even in a compromise scenario, a new lot would still have to be created, and it would require some kind of survey and access arrangement that does not overlap with the cemetery easement.
βThereβs just so many barriers,β he said, recommending that the owners contact a local surveyor to explore possible options.
No formal action was taken by the commission, as the discussion was informational only.
Other Business
Commissioners approved the site plan submitted by Kevin and Tracy McArthur to build a single-family home on Lot 113 of Southern Shores Subdivision.
βIt meets the lake setback,β Bunton said, βand all requirements specified for a site plan are met.β

The McArthurs were reminded that a post-construction site plan must also be submitted within a year of the pre-construction approval.
Aaron Keller also received approval to build a single-family home on Lot 11 of the M & M Lakeside Subdivision. Bunton said this plan also met all zoning requirements, including lake setbacks.
The next meeting of the Lake Planning Commission is scheduled for July 24 at 1:30 p.m.